Inkers
Case Study · Commercial

Twelve footings saved from demolition before the first column was poured

A 3.5 lakh sq ft Grade-A commercial development where a benchmarking error created a 1m footing offset — caught and corrected against IS-456 tolerances before structural work proceeded.

Powered by Kael
Foundation footings on a commercial construction site

12

Footings retained, not demolished

0

Critical-path days lost

3.5 lakh sq ft

Grade-A commercial

Project Brief

Type

Grade-A Commercial Development

Scale

3,50,000 Sq Ft

Project Cost

₹120 Crore

(₹3,400 per sq ft constr.)

The brief

A premium 3.5 lakh sq ft commercial development with G+12 RCC framing. The project demanded high-quality structural delivery and a programme with very little contingency for foundation rework.

Why it was risky

Foundation errors are unforgiving. A 1 m horizontal offset on a single footing typically forces column line redesign, and late corrections cascade into beam, slab, and façade geometry. The standard structural-consultant response — when an offset is caught after pour — is demolition.

  • Footing offset: an incorrect benchmark on the layout drawing translated into a 1 m horizontal misalignment across twelve footings.
  • Structural rework: the consultant's first-instinct mitigation was demolition and re-pour, on every affected footing.
  • Execution delay: each demolished footing would have removed roughly four weeks from the column line above it.
  • Cost escalation: demolition, debris handling, fresh excavation, and re-pour for twelve footings would have priced into the high single-digit crores and forced a programme reset.

What Kaël did

  • Digital hold points were enforced at the layout stage — no footing reinforcement could begin until the layout had been signed off against the GFC drawings.
  • Coordinate verification ran the site survey against the structural model before any pour, surfacing the 1 m benchmarking error within hours of the first layout being marked.
  • Photo evidence was captured at every layout, giving the structural consultant the data they needed to assess each footing against IS-456 tolerance bands rather than defaulting to demolition.
  • Instant feedback turned what would have been a multi-week issue into a same-day field correction.

Outcome

All twelve footings were retained. The structural programme stayed on its critical path, the column lines above were poured to the original schedule, and the demolition cost line never appeared on the project register.

Impact

12 Footings

Saved from demolition

Programme

Critical path protected, no slippage

Construction is changing. Are you?

We work closely with every client to understand the specific project before anything else. Tell us what you're building.